REPAIR/REHAB CIVIC CENTER DAO, CAPIZ

Project Code : R1-13-06-19-02-000-3
Project Description : Dao Social Hall is one of the most used facility in the Municipality were big activities is being held after it was hit by typhoon Yolanda, with this eventuality the Municipality has no more place to accommodate big events. Thus, The Rehabilitation of Dao Civic Center is one of the project submitted by Municipality of Dao under RAY program of DILG, with a total amount of Php 5 Million Pesos. That will cover expenses on the following activities such as; 1. Demolition of Damaged Structure and Clearing 2. Concrete/ Masonry Works and Repair of Trusses and Total replacement of Roofing's. The restoration of this project will surely bring back dynamic of convergence of the people to continue to plan for the betterment of Daonhon.
Region : REGION 06 - WESTERN VISAYAS
Year : 2014
Program : Recovery Assistance on Yolanda (RAY)
Exact Location : POBLACION, DAO, CAPIZ
Project Type : Civic Center
Implementing Agency: DILG/LGU
Beneficiaries: capacity/users
Number of Beneficiaries: 2000
Number of Jobs Generated: 15

Project Status: Completed
Status:
Status Reason:
Date Submitted:
Submitted By:
Remarks: -

Risk Rating:High Risk

Risk

Risk Trigger Risk Level Risk Causes Response Action Responsibility
Poor disbursement rates High Risk RD to issue final advisory to LGU to in turn issue Termination Letter to the Contractor and impose penalty clause in the signed Contract, and PD to secure copy of Termination Letter RD/PD
Actual cost overruns High Risk RD to issue 3rd advisory to LGU to in turn issue Termination Letter to the Contractor and takeover implementation, and impose penalty clause in the signed Contract, and PD to secure copy of Termination Letter RD/PD

Dates

Target Start Date: 2014-06-03
Target Completion Date: 2014-10-09
Actual Start Date: 2014-06-03
Actual End Date: 2014-10-09

A. Physical Status

Milestones Target Actual
Sub-project Preparation
  • Approved Subproject Proposal/FS
2014-02-172014-02-17
  • MOA Signed
2014-04-082014-04-08
  • Approved DED
2014-03-052014-03-05
Procurement Process
  • Ad/ Posting ITB
2014-05-132014-05-13
  • BAC Resolution
2014-05-282014-05-28
  • Submission/ Opening of Bids
2014-05-282014-05-08
  • Issuance of Notice of Award
2014-05-302014-05-30
  • Issuance of Notice to Proceed
2014-06-032014-06-03
Construction/ Implementation
  • Start of Contract(Effectivity Date)
2014-06-032014-06-03
  • End of Contract(Completion Date)
2014-10-092014-10-09
  • Certificate of Acceptance

B. Financial Releases

Particulars Target Actual
Release of CAF
  • Amount
4,000,000.004,000.000.00
  • Date Release
2014-04-092014-04-09
First Tranche
  • Amount
4,000,000.004,000,000.00
  • Date Release
2014-04-112014-04-11
Second Tranche
  • Amount
  • Date Release

Project Costs

Allocated By National Government: Php 5,000,000.00

LGU Counterpart: Php 0.00
Financial Institution Fund: Php 0.00
Total Project Cost: Php 5,000,000.00

Charts

Physical Accomplishment

Year Month % Accomplished % Total as of the Month Total Amount Cost
2014 June0.000.00Php 0.00
August0.000.00Php 0.00
View Details

Financial Accomplishment

NG Amount Disbursed LGU Amount Disbursed FI Amount Disbursed Total
Value of Work Accomplished Php 0.00
Disbursement Php 179.00 Php 0.00 Php 129.00 Php 308.00
Balance Php -308.00