     Sub-project Preparation - Approved DED - Found Empty
     Construction/ Implementation - Certificate of Acceptance - Found Empty
     Release of CAF - Amount - Found Empty
     Release of CAF - Date Release - Found Empty
     First Tranche - Amount - Found Empty
     First Tranche - Date Release - Found Empty
     Second Tranche - Amount - Found Empty
     Second Tranche - Date Release - Found Empty
  • Replacement of Roofing (Municipal Hall)
  • 60% Replacement of Roofing (Municipal Hall)
  • Replacement of Roofing (Municipal Hall)
  • Replacement of Roofing (Municipal Hall)
  • 30% Replacement of Roofing (Municipal Hall)
  • Replacement of Roofing (Municipal Hall)30
  • Replacement of Roofing (Municipal Hall)
  • before
  • Replacement of Roofing (Municipal Hall)90
  • Replacement of Roofing (Municipal Hall)
  • Replacement of Roofing (Municipal Hall)completed
  • Replacement of Roofing (Municipal Hall)
  • Replacement of Roofing (Municipal Hall)turn over
  • Replacement of Roofing (Municipal Hall)
  • Replacement of Roofing (Municipal Hall)
  • Replacement of Roofing (Municipal Hall)
  • Replacement of Roofing (Municipal Hall)

REPAIR/REHAB MUNICIPAL HALL TIBIAO, ANTIQUE

Project Code : R1-13-06-06-17-000-1
Project Description : Detach damaged purlins and old roofing, install new roofing, replace damaged ceiling joist / ceiling board and painting.
Region : REGION 06 - WESTERN VISAYAS
Year : 2014
Program : Recovery Assistance on Yolanda (RAY)
Exact Location : Poblacion, Tibiao, Antique
Project Type : Municipal Hall
Implementing Agency: LGU Tibiao, Antique
Beneficiaries: Municipal officials
Number of Beneficiaries: 100
Number of Jobs Generated: 25

Project Status: Completed
Status:
Status Reason:
Date Submitted:
Submitted By:
Remarks: 79.50

Risk Rating:No Risk

Dates

Target Start Date: 2014-08-12
Target Completion Date: 2014-10-11
Actual Start Date: 2014-08-12
Actual End Date: 0000-00-00

A. Physical Status

Milestones Target Actual
Sub-project Preparation
  • Approved Subproject Proposal/FS
2014-04-102014-04-10
  • MOA Signed
2014-04-112014-04-11
  • Approved DED
Procurement Process
  • Ad/ Posting ITB
2014-06-032014-06-03
  • BAC Resolution
2014-07-082014-07-08
  • Submission/ Opening of Bids
2014-06-232014-06-23
  • Issuance of Notice of Award
2014-07-092014-07-09
  • Issuance of Notice to Proceed
2014-07-102014-07-10
Construction/ Implementation
  • Start of Contract(Effectivity Date)
2014-08-122014-08-12
  • End of Contract(Completion Date)
2014-10-112014-10-11
  • Certificate of Acceptance

B. Financial Releases

Particulars Target Actual
Release of CAF
  • Amount
  • Date Release
First Tranche
  • Amount
  • Date Release
Second Tranche
  • Amount
  • Date Release

Project Costs

Allocated By National Government: Php 1,000,000.00

LGU Counterpart: Php 0.00
Financial Institution Fund: Php 0.00
Total Project Cost: Php 1,000,000.00

Charts

Physical Accomplishment

Year Month % Accomplished % Total as of the Month Total Amount Cost
2014 August15.5115.51Php 155,085.94
September38.1753.68Php 381,735.61
View Details

Financial Accomplishment

NG Amount Disbursed LGU Amount Disbursed FI Amount Disbursed Total
No financial accomplishments yet