Please update the details of this project!

     Sub-project Preparation - Approved Subproject Proposal/FS - Found Empty
     Sub-project Preparation - Approved DED - Found Empty
     First Tranche - Amount - Found Empty
     First Tranche - Date Release - Found Empty
     Second Tranche - Amount - Found Empty
     Second Tranche - Date Release - Found Empty
  • before
  • Front Side Photo of the Municipal Hall Before the Repair
  • Top View Photo of the Municipal Hall. Before the Repair..
  • Interior Ceiling Before the Repair
  • Exterior Ceiling Before the Repair
  • billboard,30%
  • Repair of Roof..
  • Repair of Roof..30
  • At 60% Accomplishment
  • Repair of Exterior Ceiling (at 30% Accomplished)
  • Photos of Scaffolding 90
  • turn over
  • completed

REPAIR/REHAB OF MUNICIPAL HALL LIBERTAD, ANTIQUE

Project Code : R1-13-06-06-10-000-1
Project Description : Repair of roofing Works, Interior and Exterior Ceiling and Paints Works
Region : REGION 06 - WESTERN VISAYAS
Year : 2014
Program : Recovery Assistance on Yolanda (RAY)
Exact Location : Centro Weste, Libertad, Antique
Project Type : Municipal Hall
Implementing Agency: Municipal Engineering Office, Department of the Interior and Local Government
Beneficiaries: Municipal officials
Number of Beneficiaries: 100
Number of Jobs Generated: 10

Project Status: Completed
Status:
Status Reason:
Date Submitted:
Submitted By:
Remarks: -

Risk Rating:High Risk

Risk

Risk Trigger Risk Level Risk Causes Response Action Responsibility
Poor disbursement rates High Risk RD to issue final advisory to LGU to in turn issue Termination Letter to the Contractor and impose penalty clause in the signed Contract, and PD to secure copy of Termination Letter RD/PD
Actual cost overruns High Risk RD to issue 3rd advisory to LGU to in turn issue Termination Letter to the Contractor and takeover implementation, and impose penalty clause in the signed Contract, and PD to secure copy of Termination Letter RD/PD

Dates

Target Start Date: 2014-07-14
Target Completion Date: 2014-08-28
Actual Start Date: 2014-07-14
Actual End Date: 2014-09-01

A. Physical Status

Milestones Target Actual
Sub-project Preparation
  • Approved Subproject Proposal/FS
  • MOA Signed
2014-04-112014-04-11
  • Approved DED
Procurement Process
  • Ad/ Posting ITB
2014-06062014-06-13
  • BAC Resolution
2014-07-01
  • Submission/ Opening of Bids
2014-06-26
  • Issuance of Notice of Award
2014-07-02
  • Issuance of Notice to Proceed
2014-07-08
Construction/ Implementation
  • Start of Contract(Effectivity Date)
2014-07-082014-07-14
  • End of Contract(Completion Date)
2014-08-202014-09-01
  • Certificate of Acceptance
2014-09-03

B. Financial Releases

Particulars Target Actual
Release of CAF
  • Amount
600000.00
  • Date Release
2014-04-11
First Tranche
  • Amount
  • Date Release
Second Tranche
  • Amount
  • Date Release

Project Costs

Allocated By National Government: Php 600,000.00

LGU Counterpart: Php 0.00
Financial Institution Fund: Php 0.00
Total Project Cost: Php 600,000.00

Charts

Physical Accomplishment

Year Month % Accomplished % Total as of the Month Total Amount Cost
2014 August50,523.1350,523.13Php 302,633.52
September48.5750,571.69Php 291,404.06
View Details

Financial Accomplishment

NG Amount Disbursed LGU Amount Disbursed FI Amount Disbursed Total
Value of Work Accomplished Php 594,037.58
Disbursement Php 594,037.59 Php 0.00 Php 0.00 Php 594,037.59
Balance Php -0.01
View Details

Comments








*