REPAIR/REHAB MUNICIPAL HALL NEW WASHINGTON, AKLAN

Project Code : R1-13-06-04-15-000-1
Project Description : Repair of Steel roofing system, painting works and windows glasses
Region : REGION 06 - WESTERN VISAYAS
Year : 2014
Program : Recovery Assistance on Yolanda (RAY)
Exact Location : Poblacion, New Washington, Aklan
Project Type : Municipal Hall
Implementing Agency: LGU, New Washington, Aklan
Beneficiaries: Municipal officials
Number of Beneficiaries: 0
Number of Jobs Generated: 13

Project Status: Completed
Status:
Status Reason:
Date Submitted:
Submitted By:
Remarks: -

Risk Rating:No Risk

Dates

Target Start Date: 2014-06-13
Target Completion Date: 2014-10-10
Actual Start Date: 0000-00-00
Actual End Date: 0000-00-00

A. Physical Status

Milestones Target Actual
Sub-project Preparation
  • Approved Subproject Proposal/FS
2014-02-20
  • MOA Signed
2014-02-202014-04-11
  • Approved DED
Procurement Process
  • Ad/ Posting ITB
2014-04-23
  • BAC Resolution
2014-05-29
  • Submission/ Opening of Bids
2014-05-21
  • Issuance of Notice of Award
2014-06-13
  • Issuance of Notice to Proceed
2014-06-13
Construction/ Implementation
  • Start of Contract(Effectivity Date)
2014-06-13
  • End of Contract(Completion Date)
2014-10-10
  • Certificate of Acceptance

B. Financial Releases

Particulars Target Actual
Release of CAF
  • Amount
364,801.40
  • Date Release
6/23/2014
First Tranche
  • Amount
510,733.60
  • Date Release
7/30/2014
Second Tranche
  • Amount
  • Date Release

Project Costs

Allocated By National Government: Php 1,518,303.00

LGU Counterpart: Php 0.00
Financial Institution Fund: Php 0.00
Total Project Cost: Php 1,518,303.00

Physical Accomplishment

No physical accomplishments yet

Financial Accomplishment

NG Amount Disbursed LGU Amount Disbursed FI Amount Disbursed Total
No financial accomplishments yet