Sub-project Preparation - Approved Subproject Proposal/FS - Found Empty
Sub-project Preparation - MOA Signed - Found Empty
Sub-project Preparation - Approved DED - Found Empty
Procurement Process - Ad/ Posting ITB - Found Empty
Procurement Process - BAC Resolution - Found Empty
Procurement Process - Submission/ Opening of Bids - Found Empty
Procurement Process - Issuance of Notice of Award - Found Empty
Procurement Process - Issuance of Notice to Proceed - Found Empty
Construction/ Implementation - Start of Contract(Effectivity Date) - Found Empty
Construction/ Implementation - End of Contract(Completion Date) - Found Empty
Construction/ Implementation - Certificate of Acceptance - Found Empty
Release of CAF - Amount - Found Empty
Release of CAF - Date Release - Found Empty
Second Tranche - Date Release - Found Empty
REPAIR/REHAB PUBLIC MARKET NABAS, AKLAN
Project Code : R1-13-06-04-14-000-2
Project Description : Reapair of Steel Roofing System and painting works.
Region : REGION 06 - WESTERN VISAYAS
Year : 2014
Program : Recovery Assistance on Yolanda (RAY)
Exact Location : POBLACION
Project Type : Public Market
Implementing Agency: LGU
Beneficiaries: vendors,stall owners
Number of Beneficiaries: 0
Number of Jobs Generated: 0
Project Status: Completed
Status:
Status Reason:
Date Submitted:
Submitted By:
Remarks: -
Risk Rating:
Dates
Target Start Date: 0000-00-00
Target Completion Date: 0000-00-00
Actual Start Date: 0000-00-00
Actual End Date: 0000-00-00
A. Physical Status
Milestones | Target | Actual |
---|---|---|
Sub-project Preparation | ||
| ||
| ||
| ||
Procurement Process | ||
| ||
| ||
| ||
| ||
| ||
Construction/ Implementation | ||
| ||
| ||
|
B. Financial Releases
Particulars | Target | Actual |
---|---|---|
Release of CAF | ||
| ||
| ||
First Tranche | ||
| 1,000,000.00 | 800,000.00 |
| 11-Apr-14 | 11-Apr-14 |
Second Tranche | ||
| 200,000.00 | 200,000.00 |
|
Project Costs
Allocated By National Government: Php 1,000,000.00
LGU Counterpart: Php 0.00
Financial Institution Fund: Php 0.00
Total Project Cost: Php 1,000,000.00
Physical Accomplishment
No physical accomplishments yet |
Financial Accomplishment
NG Amount Disbursed | LGU Amount Disbursed | FI Amount Disbursed | Total | ||||||
---|---|---|---|---|---|---|---|---|---|
No financial accomplishments yet |