Sub-project Preparation - Approved Subproject Proposal/FS - Found Empty
Construction/ Implementation - Certificate of Acceptance - Found Empty
First Tranche - Amount - Found Empty
First Tranche - Date Release - Found Empty
Second Tranche - Amount - Found Empty
Second Tranche - Date Release - Found Empty
REPAIR/REHAB CIVIC CENTER LEZO, AKLAN
Project Code : R1-13-06-04-08-000-1
Project Description : REPAIR OF ROOFING
Region : REGION 06 - WESTERN VISAYAS
Year : 2014
Program : Recovery Assistance on Yolanda (RAY)
Exact Location : Brgy. Poblacion, Lezo, Aklan
Project Type : Civic Center
Implementing Agency: DILG
Beneficiaries: capacity/users
Number of Beneficiaries: 0
Number of Jobs Generated: 12
Project Status: Completed
Status:
Status Reason:
Date Submitted:
Submitted By:
Remarks: -
Risk Rating:
Dates
Target Start Date: 2014-09-05
Target Completion Date: 2014-10-05
Actual Start Date: 2014-09-15
Actual End Date: 0000-00-00
A. Physical Status
Milestones | Target | Actual |
---|---|---|
Sub-project Preparation | ||
| ||
| 2014-4-10 | 2014-4-10 |
| - | - |
Procurement Process | ||
| 2014-7-1 | 2014-7-14 |
| 2014-8-14 | 2014-8-14 |
| 2014-8-8 | 2014-8-8 |
| 2014-8-15 | 2014-8-15 |
| 2014-8-20 | 2014-8-20 |
Construction/ Implementation | ||
| 2014-9-5 | 2014-9-15 |
| 2014-10-5 | |
|
B. Financial Releases
Particulars | Target | Actual |
---|---|---|
Release of CAF | ||
| 500000 | 500000 |
| April 11, 2014 | April 11, 2014 |
First Tranche | ||
| ||
| ||
Second Tranche | ||
| ||
|
Project Costs
Allocated By National Government: Php 500,000.00
LGU Counterpart: Php 0.00
Financial Institution Fund: Php 0.00
Total Project Cost: Php 500,000.00
Physical Accomplishment
No physical accomplishments yet |
Financial Accomplishment
NG Amount Disbursed | LGU Amount Disbursed | FI Amount Disbursed | Total | ||||||
---|---|---|---|---|---|---|---|---|---|
No financial accomplishments yet |
Comments