REPAIR/REHAB PUBLIC MARKET BANGA, AKLAN

Project Code : R1-13-06-04-03-000-2
Project Description : REHABILITATION OF DAMAGED EXISTING ROOFING, SITE DEMOLITION OF ROOFING, ROOF FRAMING AND ROOFING WORKS
Region : REGION 06 - WESTERN VISAYAS
Year : 2014
Program : Recovery Assistance on Yolanda (RAY)
Exact Location : Poblacion, Banga, Aklan
Project Type : Public Market
Implementing Agency: LGU
Beneficiaries: vendors,stall owners
Number of Beneficiaries: 40
Number of Jobs Generated: 16

Project Status: Completed
Status:
Status Reason:
Date Submitted:
Submitted By:
Remarks: Beneficiaries Feedback

Risk Rating:High Risk

Risk

Risk Trigger Risk Level Risk Causes Response Action Responsibility
Actual cost overruns High Risk RD to issue 3rd advisory to LGU to in turn issue Termination Letter to the Contractor and takeover implementation, and impose penalty clause in the signed Contract, and PD to secure copy of Termination Letter RD/PD

Dates

Target Start Date: 2014-06-15
Target Completion Date: 2014-07-29
Actual Start Date: 2014-06-15
Actual End Date: 2014-08-05

A. Physical Status

Milestones Target Actual
Sub-project Preparation
  • Approved Subproject Proposal/FS
  • MOA Signed
  • Approved DED
Procurement Process
  • Ad/ Posting ITB
2014-05-8-14
  • BAC Resolution
2014-05-30
  • Submission/ Opening of Bids
2014-05-30
  • Issuance of Notice of Award
2014-06-03
  • Issuance of Notice to Proceed
2014-06-09
Construction/ Implementation
  • Start of Contract(Effectivity Date)
2014-06-15
  • End of Contract(Completion Date)
2014-07-292014-08-08
  • Certificate of Acceptance
2014-08-08

B. Financial Releases

Particulars Target Actual
Release of CAF
  • Amount
  • Date Release
First Tranche
  • Amount
P400,000.00
  • Date Release
April 11, 2014
Second Tranche
  • Amount
  • Date Release

Project Costs

Allocated By National Government: Php 400,000.00

LGU Counterpart: Php 0.00
Financial Institution Fund: Php 0.00
Total Project Cost: Php 400,000.00

Charts

Physical Accomplishment

Year Month % Accomplished % Total as of the Month Total Amount Cost
2014 August100.00100.00Php 400,000.00
View Details

Financial Accomplishment

NG Amount Disbursed LGU Amount Disbursed FI Amount Disbursed Total
Value of Work Accomplished Php 400,000.00
Disbursement Php 399,382.50 Php 0.00 Php 0.00 Php 399,382.50
Balance Php 617.50