Item Item Weight Total Value Cost Total QTY Target QTY Accomplishment % QTY Accomplished % Accomplishment % Date Status
DEMOLITION OF DILAPIDATED ROOFING 9.00% Php 45,000.00 1 Lot 0.1613 Lot 16.13% 0.1613 Lot 16.13% 1.45% 2014-10-18
ROOFING 74.82% Php 374,120.00 963 sq.m. 0.1613 sq.m. 0.02% 0.1613 sq.m. 0.02% 0.01% 2014-10-18
REPAIR OF TOILET (MALE & FEMALE), DOWNSPOUT G/FLR. 4.42% Php 22,091.00 1 Lot 0.1936 Lot 19.36% 0.1936 Lot 19.36% 0.86% 2014-10-18
REPAIR OF TOILET (MALE & FEMALE),DOWN SPOUT 2ND /FLR. 4.85% Php 24,262.00 1 Lot 0.1936 Lot 19.36% 0.1936 Lot 19.36% 0.94% 2014-10-18
REPAIR OF TOILET (MALE & FEMALE),DOWN SPOUT 3RD /FLR. 4.01% Php 20,027.00 1 Lot 0.1936 Lot 19.36% 0.1936 Lot 19.36% 0.78% 2014-10-18
Total Physical Accomplishment: 4.03% Total Amount Work Accomplished Php 20,172.33