Item Item Weight Total Value Cost Total QTY Target QTY Accomplishment % QTY Accomplished % Accomplishment % Date Status
CONCRETE WORKS 26.09% Php 391,350.00 36 cu.m. 36 cu.m. 100.00% 36 cu.m. 100.00% 26.09% 2014-08-25
CHB WALL AND PLASTERING 15.60% Php 234,050.00 239 sq.m. 239 sq.m. 100.00% 239 sq.m. 100.00% 15.60% 2014-08-30
FORMS AND FALSE WORKS 2.34% Php 35,100.00 1 lot 1 lot 100.00% 1 lot 100.00% 2.34% 2014-07-22
ROOFINGS AND ROOF FRAMINGS 21.68% Php 325,198.00 176 sq.m. 176 sq.m. 100.00% 176 sq.m. 100.00% 21.68% 2014-08-25
DOORS AND WINDOWS 7.49% Php 112,400.00 21 sq.m. 21 sq.m. 100.00% 21 sq.m. 100.00% 7.49% 2014-08-28
DEMOLITION OF DAMAGED & UNSTABLE PARTS OF THE BUILDING 11.07% Php 166,077.00 1 lot 1 lot 100.00% 1 lot 100.00% 11.07% 2014-07-10
ELECTRICAL WORKS 8.46% Php 126,825.00 1 lot 1 lot 100.00% 1 lot 100.00% 8.46% 2014-09-7
PLUMBING 7.27% Php 109,000.00 1 lot 1 lot 100.00% 1 lot 100.00% 7.27% 2014-09-7
Total Physical Accomplishment: 100.00% Total Amount Work Accomplished Php 1,500,000.00