Item Item Weight Total Value Cost Total QTY Target QTY Accomplishment % QTY Accomplished % Accomplishment % Date Status
CHB Walling/Lintel Beam 10.63% Php 103,466.00 82 square meter 82 square meter 100.00% 82 square meter 100.00% 10.63% 2014-08-12
Plaster Finishing 3.34% Php 32,475.00 185 square meter 185 square meter 100.00% 185 square meter 100.00% 3.34% 2014-08-12
Forms and Scaffoldings 2.32% Php 22,615.00 17 square meter 17 square meter 100.00% 17 square meter 100.00% 2.32% 2014-08-12
Partition (SB Office) 12.35% Php 120,235.00 133 square meter 110 square meter 82.71% 110 square meter 82.71% 10.21% 2014-08-12
Roof Flashing 0.56% Php 5,440.00 17 square meter 17 square meter 100.00% 17 square meter 100.00% 0.56% 2014-08-12
Windows 28.81% Php 280,556.00 5788 square ft 4630 square ft 79.99% 4630 square ft 79.99% 23.05% 2014-08-12
Windows Grill 8.40% Php 81,831.00 560 square ft 560 square ft 100.00% 560 square ft 100.00% 8.40% 2014-08-12
Ceiling (VM/Session Hall) 3.64% Php 35,464.00 140 square meter 139.7 square meter 99.79% 139.7 square meter 99.79% 3.63% 2014-08-12
Electrical 13.40% Php 130,460.00 1 lot 0.52 lot 52.00% 0.52 lot 52.00% 6.97% 2014-08-12
Total Physical Accomplishment: 69.11% Total Amount Work Accomplished Php 672,922.10