Item Item Weight Total Value Cost Total QTY Target QTY Accomplishment % QTY Accomplished % Accomplishment % Date Status
Roofing and Concrete Gutter 100.00% Php 121,635.29 1 LOT 1 LOT 100.00% 0.9 LOT 90.00% 90.00% 2014-08-30
Total Physical Accomplishment: 90.00% Total Amount Work Accomplished Php 109,471.76