Item | Item Weight | Total Value Cost | Total QTY | Target QTY Accomplishment | % | QTY Accomplished | % | Accomplishment % | Date | Status | |
---|---|---|---|---|---|---|---|---|---|---|---|
ROOFING | 62.92% | Php 85,432.20 | 1 LOT | 1 LOT | 100.00% | 1 LOT | 100.00% | 62.92% | 2014-07-10 | ![]() | |
CHB WALL | 37.08% | Php 50,341.80 | 72 SQ.M | 72 SQ.M | 100.00% | 70 SQ.M | 97.22% | 36.05% | 2014-07-09 | ![]() | |
Total Physical Accomplishment: | 98.97% | Total Amount Work Accomplished | Php 134,375.62 |