Item Item Weight Total Value Cost Total QTY Target QTY Accomplishment % QTY Accomplished % Accomplishment % Date Status
removed and installation of roofing 66.34% Php 663,400.00 461 sq.m. 107.77 sq.m. 23.38% 107.77 sq.m. 23.38% 15.51% 2014-08-26
removed and installation of roofing 66.34% Php 663,400.00 461 sq.m. 229.96 sq.m. 49.88% 229.96 sq.m. 49.88% 33.09% 2014-09-11
removed and installation of roofing 66.34% Php 663,400.00 461 sq.m. 35.31 sq.m. 7.66% 35.31 sq.m. 7.66% 5.08% 2014-09-18
Total Physical Accomplishment: 53.68% Total Amount Work Accomplished Php 536,821.55