Item Item Weight Total Value Cost Total QTY Target QTY Accomplishment % QTY Accomplished % Accomplishment % Date Status
Replacement of G.I Roofing and Outside Ceiling 89.91% Php 764,273.00 1 lot 0.5 lot 50.00% 0.5 lot 50.00% 44.96% 2014-08-31
Replacement of Ceiling at Ground Floor and Second Floor (partial) 4.40% Php 37,375.00 1 lot 0.025 lot 2.50% 0.025 lot 2.50% 0.11% 2014-08-31
Repainting of Truss and Ceiling of Ground Floor Lobby 3.54% Php 30,060.00 1 lot 0 lot 0.00% 0 lot 0.00% 0.00% 2014-08-31
Total Physical Accomplishment: 45.07% Total Amount Work Accomplished Php 383,070.88