Item Item Weight Total Value Cost Total QTY Target QTY Accomplishment % QTY Accomplished % Accomplishment % Date Status
Roofing Insulation 11.14% Php 27,840.00 1 lot 1 lot 100.00% 1 lot 100.00% 11.14% 2014-07-01
Electrical 10.59% Php 26,485.00 1 lot 1 lot 100.00% 1 lot 100.00% 10.59% 2014-07-21
Painting 10.72% Php 26,800.00 1 lot 1 lot 100.00% 1 lot 100.00% 10.72% 2014-07-22
Skylight Roofing 37.74% Php 94,338.00 1 lot 1 lot 100.00% 1 lot 100.00% 37.74% 2014-07-14
Removal/Disposal of Damaged Materials 2.52% Php 6,300.00 1 lot 1 lot 100.00% 1 lot 100.00% 2.52% 2014-07-24
Direct Cost 0.00% Php 0.00 0 lot 0 lot nan% 0 lot nan% nan% 2014-10-01
Indirect Cost 18.18% Php 45,440.75 1 lot 1 lot 100.00% 1 lot 100.00% 18.18% 2014-10-01
Taxes 9.12% Php 22,795.25 1 lot 1 lot 100.00% 1 lot 100.00% 9.12% 2014-10-15
Total Physical Accomplishment: nan% Total Amount Work Accomplished Php 249,999.00